Do you have new solar panels and want to receive compensation for the electricity you feed into the grid as soon as possible?

The grid operator will only forward the feed-in data to the market portal from the date on which the installation has been officially registered and approved by the grid operator.

Prior to that date, you can still feed electricity into the grid, but the supplier will not receive the electricity you feed in.

This is also important for battery control: Yuso recommends that you only start battery control once the installation has been inspected.

Have you already injected into the grid prior to the inspection date? This data will not be forwarded to the supplier by Fluvius and will be lost.