Before a battery can earn from FCR, aFRR, mFRR or a capacity mechanism, it must be prequalified by the TSO. During prequalification, the TSO checks that the asset and its control systems can deliver what is promised. Typical tests cover response time, accuracy of the delivered power, availability and communication with the TSO's systems. The asset's BSP also has to meet requirements for monitoring, data exchange and operational procedures.

Prequalification is done per service, so an asset may qualify for one product before another. It usually runs in parallel with commissioning, so that the asset can enter ancillary markets soon after it starts wholesale trading at energisation. Careful preparation shortens the time between connection and full revenue, which directly affects the project's early cash flow.